South Jersey Gas Former Pleasantville MGP: Weekly Project Update – Week of 12/3/18

In April 2018, South Jersey Gas (SJG) mobilized for the current phase of remediation at the Pleasantville former Manufactured Gas Plant (MGP) Site in Pleasantville, New Jersey. The Site is located at the intersection of North Franklin Boulevard and Old Turnpike. It is anticipated that activities will take approximately 14 months to complete.

South Jersey Gas is committed to open communications with community leaders, government officials, residents and local businesses. For more information on the project, visit http://pleasantvillemgp.com/. For questions or concerns, please call the project information line at (609) 833-2810 or email us at comments@pleasantvillemgp.com.

Locations of 2018 Project Stages

Stage 1A: South of Old Turnpike, East of North Franklin, North of Grant

Stage 2: South of Old Turnpike, west of North Franklin, North of Grant

Work to be performed: December 3-7

Site Activity

  • Begin to prepare Stage 2 for remediation.
  • Continue ISS (in-situ stabilization, or the use of stabilization constituents to contain materials onsite) within Stage 1A.
  • Utilities to continue relocation of overhead utility lines and poles.
  • Begin removal of South Jersey Gas storage building.
  • Continue to remove South Jersey Gas meter station.
  • As necessary, continue efforts to mitigate odors naturally associated with MGP materials, including foaming, maintaining fixed perimeter odor-neutralizing granule system, and conducting daily odor assessment patrols.
  • As necessary, continue water misting to reduce dust.
  • Continue air monitoring at site perimeter.
  • Continue onsite security (weekdays: 4 p.m. – 7 a.m. and Sat/Sun: 24-hrs.).


Work performed: November 26-30

Site Activity

  • Continued preparing for removal of South Jersey Gas storage building.
  • Continued to remove South Jersey Gas former meter station.
  • Continued ISS (in-situ stabilization, or the use of stabilization constituents to contain materials onsite) within Stage 1A.
  • Utilities continued relocation of overhead utility lines and poles.
  • As necessary, continued efforts to mitigate odors naturally associated with MGP materials, as necessary. This includes foaming, maintaining fixed perimeter odor-neutralizing granule system, and conducting daily odor assessment patrols.
  • Continued water misting to reduce dust, as necessary.
  • Continued air monitoring at site perimeter.
  • Continued onsite security (weekdays: 4 p.m. – 7 a.m. and Sat/Sun: 24-hrs.).